Bushehr Petchem Phase 1 by Yearend: CEO

Bushehr Petchem Phase 1 by Yearend: CEO
TEHRAN, March 30 (Shana) – Managing director of the Busher Petrochemical Plant’s construction project said that following activation of the project’s 1.9-billion-euro finance, the first phase will be launched by end of the year (March 20).
Gholamreza Mostajaboldaveh said that Phase 1 with methanol and utility units is underway with a 60 percent progress.
Engineering procedures of Phase 2 for production of polyethylene and elfin will be finalized in near future, he said.
“Phase 2 has a progress of 10 percent and purchasing its equipment has started,” he said, adding that Phase 3 will designed for acid acetic and monomers.
Apr 4, 2016 11:48
shana |
Number of visit : 544

Comments

Sender name is required
Email is required
Characters left: 500
Comment is required
  • Iran, Tehran, Africa Boulevard (South), after Hemmat Bridge, corner of 9 Gandi St., No. 38 (Iran Petrochemical Commercial Building), 2nd floor
  • 021-91008030
  • Iran - Assaluyeh - Phase 2 National Petrochemical Lands - next to Styrene Park
  • info@tjpa-pc.com