Dec 4, 2021 22:28

Bushehr Petchem Phase 1 by Yearend: CEO

Bushehr Petchem Phase 1 by Yearend: CEO
TEHRAN, March 30 (Shana) – Managing director of the Busher Petrochemical Plant’s construction project said that following activation of the project’s 1.9-billion-euro finance, the first phase will be launched by end of the year (March 20).
Gholamreza Mostajaboldaveh said that Phase 1 with methanol and utility units is underway with a 60 percent progress.
Engineering procedures of Phase 2 for production of polyethylene and elfin will be finalized in near future, he said.
“Phase 2 has a progress of 10 percent and purchasing its equipment has started,” he said, adding that Phase 3 will designed for acid acetic and monomers.
Apr 4, 2016 11:48
shana |
Number of visit : 604

Comments

Sender name is required
Email is required
Characters left: 500
Comment is required
  • Headquarter Address: No.23 (Park Center Complex), 8th Narenjestan St., Farmaniyeh crossroad, Tehran, Iran
  • +98 21 91008030
  • Next to Styrene Park, Phase 2 National Petrochemical Lands, Assaluyeh, Iran
  • info@tjpa-pc.com