Jul 29, 2021 19:39

Plant Eyes 1.75mt Urea Output Boost by Yearend

Plant Eyes 1.75mt Urea Output Boost by Yearend
Pardis Petrochemical Plant will launch its third phase by the end of the current Iranian calendar year to March 20 2017, adding 1.75 million tons/year to its urea output and 680,000 tons to its annual ammonia output.
Speaking to NIPNA, Bahman Zamani, the plant's managing director, said Pardis Plant is currently swapping 10,000 tons of petrochemicals with three other plants, namely Shiraz, Kermashah and Khorasan plants.

Phase III of the plant is 93.75% complete and is almost ready for startup.

Pardis Petrochemical Plant along with Kavian, Takht Jamshid, Polystyrene, Entekhab and Kaveh Methanol projects are some of the projects that will come online by the calendar yearend, adding 4.6mt/y to the total production capacity.


Sep 24, 2016 15:19
NIPNA |
Number of visit : 860

Comments

Sender name is required
Email is required
Characters left: 500
Comment is required
  • Iran, Tehran, Africa Boulevard (South), after Hemmat Bridge, corner of 9 Gandi St., No. 38 (Iran Petrochemical Commercial Building), 2nd floor
  • 021-91008030
  • Iran - Assaluyeh - Phase 2 National Petrochemical Lands - next to Styrene Park
  • info@tjpa-pc.com